Astara Water Supply From Chalvand River |
Introduction: |
|
Client: |
Guilan Water & Wastewater Company |
Contractor(s): |
|
Population served: |
168,700 |
Raw Water Volume: |
420 Lit/s |
Scope Of Installations: |
Diversion Dam - Raw water pumping Station - Treatment plant - Head Reservoirs-Transmission lines |
Length Of Transmission Lines: |
Approx. 19 Km |
Material & Diameter Of Pipes: |
Ductil Iron - 700 & 800 mm |
Capacity Of Reservoirs: |
1500 & 5000 m³ |
Treatment Method: |
Conventional |
Execution Cost: |
IRR 212 B |
|