Water Transmission Design Critera Revise For Central & Eastern Guilan Townships
Introduction: Feasibility study & environmental justification for execution of wastewater project.
Client: Guilan Regional Water Authority
Contractor(s):
Population served: 2,300,000 (Final Stage)
Total Water Demand: 650,000 m³/day
Major Water Sources: Mainly Sephidroud River (85%)
Location Of Treatment Plants: Sangar & Rasht- Ghazvin Roud
Capacity Of Treatment Plants: Totally 6,600 Lit/s
Length Of Transmission Pipelines: Approx.450 Km
Diameter OF Transmission Pipelines: 400 mm to 1250 mm
Material Of Transmission Pipes: Ductil Iron & Prepacked concrete
Execution Cost: