Construction Of Aliaabad Wastewater Treatment Plant |
Introduction: |
Wastewater collection , Treatment & disposal of Aliabad city . |
Client: |
Golestan Water & Wastewater Company |
Contractor(s): |
|
Population served: |
78,200 (1st phase) |
Population served: |
92,000 (2nd phase) |
Total Flow: |
15,800 m³/day (1st phase) |
Total Flow: |
19,320 m³/day (2nd phase) |
Treatment Method: |
Activated Sludge - Extended Aeration |
Execution Cost: |
IRR 83,100 m |
|