Home Projects Employees List Upload Download Email Contact us

Project Details
Shiraz Water Transmition Line to Zone 19 - 2
Client: Shiraz water and wastewater company
Contractor(s): Goupleh Co.
Total Cost: 26,168,324,000 Rial
Contract duration: 20 month
Length Of Mains: 11.5 Km
Diameter OF Transmission Lines: 800 mm - GRP
Start Date: 85/01/26
Current Situation: Finished


< Back To The List Of Projects


Home | Projects | Employees List | Upload | Download | Email | Contact us
Copyright © 2003-2004, All rights reserved.
Designed and developed by ARTem